Matanzas will install sectionalizers and add neighborhoods to blackout rotations

The work seeks to separate hospital circuits and redistribute 19 megawatts now kept on protected lines.

2 min read

Editorial visual recreation for Matanzas installing sectionalizers and adding neighborhoods to blackout rotations
Illustration: Malecón90

Electric-sector authorities in Matanzas plan to install 12 sectionalizers to reorganize energy distribution. The work will separate circuits serving hospitals from nearby residential areas and allow more neighborhoods to enter the blackout schedule. Manzano is among the places that will become subject to rotation. Part of the energy currently kept on protected circuits can then be assigned elsewhere.

Alejandro Rodríguez Azpeitía, director of the Provincial Electric Company, said installing the equipment would release 19 megawatts. That capacity, now tied to protected circuits, would join distribution among other zones. The plan aims to distribute electricity more evenly and reduce the time neighborhoods lack service. Twelve sectionalizers are planned.

Separating hospital lines from adjacent residential areas is a central objective. According to the announcement, health facilities would stop sharing those circuits with nearby neighborhoods, which would then enter rotation schedules. The plan combines isolation of health institutions with redistribution of energy currently reserved for those lines.

Adding Manzano shows that the system will reach residential areas previously outside the rotation associated with protected circuits. For those neighborhoods, the change means joining scheduled outages while released energy is distributed among more areas. It changes both separation of hospital lines and organization of residential blackouts.

The province also has 162 damaged transformers, according to released information. Installing sectionalizers concerns circuit distribution and energy allocation while that equipment remains affected. The announcement does not change the transformer count but places the plan in a provincial setting where authorities seek to manage available electricity differently and reduce hours without service.

Sources consulted

2 outlets
KEEP READING
Society

One recruit dies in Matanzas and another remains in critical condition after electric shock

The accident occurred at a military unit in Cidra. Another recruit was injured and his condition was reported as critical.

Society

Matanzas registers daily damage to transformers while replacement equipment is scarce

Alejandro Rodríguez Azpeitía linked part of the breakdowns to the simultaneous use of portable stations and detailed the deterioration of the network and the difficulties in manufacturing new transformers.

Society

Health of Matanzas denies a crisis in the Jagüey Grande hospital

The entity affirmed that the center maintains its services and asked to consult the official channels, but did not detail the origin of the versions or the figures mentioned.